Covenham to Boston water transfer pipeline, UK

Anglian Water identified a potential risk to residents of the growing town of Boston, UK, who could be left without water supply in the unlikely event of an extended outage at West Pinchbeck water treatment works. To protect against this eventuality and increase capacity to meet future needs, Anglian Water had planned to connect the town to a reservoir and water treatment works at Covenham, to the north, with 60km of new 600mm diameter pipeline.

Added value

A traditional solution would have cost £41.5M, with 20,700t of embodied carbon. This solution was delivered for £31.1M, with 8830t of embodied carbon. That’s a 57% carbon saving and 25% cost saving over the original plan.

It was envisaged that the first 40km of this pipeline, made from ductile iron, would loop from Covenham to the Miningsby Reservoir; the second section, constructed from polyethylene and 21km long, would run from there to Boston itself. Altogether, this new system would be able to transport 27Ml/d of treated water to the town.

But our client had set challenging cost and carbon cutting targets: building the scheme in a regular manner would make it very difficult to achieve either.

What did we do?

As a framework partner to Anglian Water’s Special Projects delivery stream, and working as part of a joint project team including contractor JN Bentley, we undertook detailed network modelling and assessment of existing assets. Our findings identified the opportunity to transfer 40% of the required water supply to Boston through existing assets to the south of the town.

This discovery meant that the new system only needed to be able to supply 15.6Ml/day. The remaining 11.4Ml/day could be unlocked from the existing assets, with some enhancements to the infrastructure. This enabled the pipeline diameter to be reduced from 600mm to 500mm for the first 40km, and to 400mm for the last 21km. This approach also allowed us to downsize a new pumping station at Covenham. Careful consideration of the pipeline route avoided the need for an intermediate booster station which may otherwise have been required.

We then analysed possible pipeline materials and installation methods. We selected polyethylene, which offered the lowest cost and embodied carbon, and which allowed for varying thickness in the pipeline wall. By optimising this thickness along the whole length of the route, we minimised material usage and cost, and reduced installation times.

The pipe was delivered in long 18m sections, reducing the number of deliveries by 30%. The choice of material meant that the pipeline was flexible enough to follow the natural terrain far better than iron or steel, which helped avoid additional joints, bends and route diversions that a more rigid pipeline would have needed.

We converted a rock trenching machine to speed excavation and reduce the width of the trench itself, minimising the volumes of excavated and backfill materials handled and reducing the impact of construction on surrounding land. Further time, cost and carbon savings were made by using excavated material as backfill, reducing the need for imported material.

How did we add value?

A traditional solution would have cost £41.5M, with 20,700t of embodied carbon. This solution was delivered for £31.1M, with 8830t of embodied carbon. That’s a 57% carbon saving and 25% cost saving.

What’s next?

Our work with leaders of the emerging low carbon agenda such as Anglian Water was one factor that led the Infrastructure Working Group of the UK government’s Green Construction Board to commission us to research and author a landmark report, the Infrastructure Carbon Review.

Throughout the process we collaborated closely with Anglian Water’s board of directors. We found that if current low carbon best practice, such as demonstrated on this project, was adopted for all UK infrastructure, there would be a £1.5bn/year economic benefit.

We are now working to raise awareness of the practical steps that businesses can take to realise carbon and cost savings, provide advice and technical support, and measure and drive for carbon and cost reductions on every major project we work on.

We use necessary cookies to make our site work. We'd also like to set optional analytics cookies to help us improve it. We won't set optional cookies unless you enable them. Using this tool will set a cookie on your device to remember your preferences.

Reject cookies Manage cookies
expand-image mail-envelope icon-icon-linkedin-mmdv-green icon-close arrow-left icon-section icon-section-white arrow-down icon-arrow-down-sml icon-arrow-left-lrg icon-arrow-left-sml icon-arrow-right-lrg icon-arrow-right-sml icon-arrow-up-sml icon-champions icon-section icon-section-white icon-download icon-education icon-email icon-grid-view icon-language icon-link-to icon-list-view icon-location icon-login-register ec-icon-login-register icon-ec-apply-arrow icon-ar-apply-arrow icon-mm-icon-search-ec icon-minus icon-more icon-phone icon-plus icon-recently-viewed icon-search icon hash key-facts-corner-sash quote-underline social-icon-facebook social-icon-googleplus social-icon-linkedin social-icon-twitter social-share-icon-facebook social-share-icon-facebook social-share-icon-googleplus social-share-icon-googleplus social-share-icon-instagram social-share-icon-instagram social-share-icon-linkedin social-share-icon-linkedin social-share-icon-twitter social-share-icon-twitter social-share-icon-youtube social-share-icon-youtube sina-weibo MM-Shape01-Quote-Views MM-Shape03-Quote-Locations MM-Shape05-Quote-Projects MM-Shape12-Quote-Sectors MM-Shape13-Quote-Expertise MM-Shape14-Quote-About-Us MM-Shape14-Quote-Careers checkmark icon-expand-view icon-apply-now menu linkedin-mmdv-green icon-ad-close mail-mmdv-green icon-ad-menu menu-close ec-menu-close sphere icon-cookies icon-legal icon-registered-companies target rotate-screen video-replay-flat video-replay audio-mute audio-play