A creative solution that made up for lost time

Renovating a pony truss bridge over the Cowanesque River required a creative approach to the temporary bridge.

Opportunity

When the pony truss bridge carrying State Route 49 over the Cowanesque River required rehabilitation, a temporary structure was needed to maintain vehicular and pedestrian traffic.

A contractor proposed to use a 132-foot-long Acrow panel bridge to maintain traffic while rehabilitating the adjoining mainline structure. However, due to the poor stability of the adjacent riverbank, the contractor could not obtain approval from PennDOT to use a proposed timber mat foundation.

Several months behind schedule, the contractor was faced with finding an alternative approach that could address the unstable riverbank condition and deal with particularly tight site constraints. These included a privately owned barn that encroached on the northeast corner of the site, a buried wingwall at the southeast corner, and two water mains.

The proposed foundation locations conflicted with existing utilities and structures. The southeast corner of the site presented an unusually challenging condition, as the southeast bearing unit of the temporary bridge was positioned above one of the existing water mains and a wingwall of the truss bridge.

Solution

The contractor contacted Mott MacDonald’s office in Pittsburgh to develop a new approach.

Working closely with the contractor, PennDOT District 3-0, and American Geotechnical and Environmental Services (our geotechnical subconsultant), Mott MacDonald developed an alternative foundation. This design allowed the contractor to finish the project within seven days of the originally scheduled completion date.

As the southeast foundation unit required relatively shallow asymmetrical geometry to straddle the wingwall and water main, we designed a steel-framed pile cap foundation to avoid modifying these existing features. At the contractor’s request, steel-framed pile caps were also developed for the other locations to expedite construction.

In addition, we developed an innovative roadway approach structure, using a geotextile-reinforced soil embankment with timber facing. These elements served as the backwalls of the bridge and reduced the lateral earth load on the bridge foundations.

Outcome

Our design was completed within two months of the notice to proceed, and construction was completed on July 10, 2013. The temporary bridge was used for four months, until October 31, 2013, while the pony truss was rehabilitated. It provided a safe alternative for the river crossing while protecting the riverbank and existing infrastructure.

We use necessary cookies to make our site work. We'd also like to set optional analytics cookies to help us improve it. We won't set optional cookies unless you enable them. Using this tool will set a cookie on your device to remember your preferences.

Reject cookies Manage cookies
expand-image mail-envelope icon-icon-linkedin-mmdv-green icon-close arrow-left icon-section icon-section-white arrow-down icon-arrow-down-sml icon-arrow-left-lrg icon-arrow-left-sml icon-arrow-right-lrg icon-arrow-right-sml icon-arrow-up-sml icon-champions icon-section icon-section-white icon-download icon-education icon-email icon-grid-view icon-language icon-link-to icon-list-view icon-location icon-login-register ec-icon-login-register icon-ec-apply-arrow icon-ar-apply-arrow icon-mm-icon-search-ec icon-minus icon-more icon-phone icon-plus icon-recently-viewed icon-search icon hash key-facts-corner-sash quote-underline social-icon-facebook social-icon-googleplus social-icon-linkedin social-icon-twitter social-share-icon-facebook social-share-icon-facebook social-share-icon-googleplus social-share-icon-googleplus social-share-icon-instagram social-share-icon-instagram social-share-icon-linkedin social-share-icon-linkedin social-share-icon-twitter social-share-icon-twitter social-share-icon-youtube social-share-icon-youtube sina-weibo MM-Shape01-Quote-Views MM-Shape03-Quote-Locations MM-Shape05-Quote-Projects MM-Shape12-Quote-Sectors MM-Shape13-Quote-Expertise MM-Shape14-Quote-About-Us MM-Shape14-Quote-Careers checkmark icon-expand-view icon-apply-now menu linkedin-mmdv-green icon-ad-close mail-mmdv-green icon-ad-menu menu-close ec-menu-close sphere icon-cookies icon-legal icon-registered-companies target rotate-screen video-replay-flat video-replay audio-mute audio-play