The pipelines will transfer liquefied petroleum gas and C5+ from the Monteiro Lobato Gas Treatment Unit to the Henrique Lage Refinery. Petrobras Petróleo SA commissioned Azevedo and Travassos Ltda. for the construction.
Challenges
Obtaining authorisation from the National Institute of Historic and Artistic Heritage (IPHAN) to begin the construction phase was essential. We worked to a very tight deadline.
Solutions
Our technical team was quickly mobilised to develop the preventive archaeology plan, which was necessary to obtain the license. Although the plan was developed in such short time, its high standard enabled IPHAN to immediately authorise the construction.
Values and benefits
The implementation of the preventive archaeology plan contributed to the protection of the historical and archaeological heritage. The heritage educational activities undertaken increased awareness among workers involved in the construction phase and members of the community.