New Irvington

A "race against time" to ensure the Bay Area's water supply

Urgently needed to guard against seismic disruption, the New Irvington Tunnel will carry drinking water to 2.6 million customers in San Francisco, San Mateo, Santa Clara, and Alameda Counties.

Award

Outstanding Public Involvement Program/Education Program, Association of Environmental Professionals (AEP)

New Irvington

Hole-through! See TunnelTalk's video report from October 2013.

Opportunity

In the late 1920s and early 1930s, miners used drill-and-blast techniques to construct the original 3.5-mile (5.6-kilometer) Irvington Tunnel between Sunol and Fremont, California. A vital part of San Francisco’s Hetch Hetchy Regional water system, the tunnel supplies approximately 85% of the City of San Francisco’s water as well as supplying other customers in the Bay Area.

But that water supply is under threat. According to Julie Labonte, director of the City’s $4.6 billion Water System Improvement Program, “Although the Hetch Hetchy water system is truly an engineering marvel, some critical elements are seismically vulnerable. It’s not a matter of if, but when a major earthquake strikes — we are truly in a race against time.”

Because the transport of water from through the tunnel to the Bay area is critically needed, the tunnel has not been dewatered and taken out of service for a physical inspection since 1966.

A new tunnel was needed to provide redundancy, but gassy ground conditions, groundwater inflows, and seismic zones with squeezing ground made the $250 million New Irvington Tunnel very challenging. “The major construction challenges will be due to groundwater,” said David Tsztoo of San Francisco Public Utilities (SFPUC) in 2011. “We have to mine into zones where we will encounter 300 static feet of groundwater.” A pre-excavation grouting program was used throughout the tunnel excavation, with over 7.8 million pounds (3.5 million kilograms) of cement injected into the ground to reduce the groundwater inflow before the ground could be excavated.

Solution

The New Irvington Tunnel was designed to parallel the original tunnel. It will be approximately 3.5 miles (5.6 kilometers) long, with a horseshoe shape and excavated dimensions of approximately 12 by 14 feet (3.6 by 4.3 meters) and a final finished inner diameter of 8.5 feet (2.6 meters) with a steel liner.

Mott MacDonald was retained as the lead consultant Construction Manager for the construction phase of this project. We assisted the SFPUC in reviewing contractor prequalifications and constructability for the bidding documents, and helped prepare the final bidding documents. We were also responsible for the following:

  • Field quality assurance inspection and testing
  • Environmental compliance monitoring and biological resource specialist monitoring
  • Field contract administration
  • Estimating, scheduling, change order, and claims management
  • Tie-in and disinfection work coordination
  • Groundwater Management Plan including preconstruction mitigation measures

The new tunnel was excavated using roadheader and drill-and-blast methods. Because of the number of fault zones, a tunnel boring machine would have run the risk of getting stuck underground in the squeezing ground normally associated with these fault zones. “The tunnel design engineers felt that there were seven zones, so seven possible chances to get stuck,” said Tsztoo.

North American Tunneling Journal reported that the project needed “old-school miners who could adapt quickly to changing ground conditions.” According to Dan McMaster, Mott MacDonald’s Construction Manager, “There have been days when we have started with drill and blast, and by that afternoon we have been into softer Class III and Class IV ground.”

In June 2012, the New Irvington Tunnel achieved its first hole-through, with teams from the Irvington Portal in Fremont and the Vargas Shaft meeting underground. “Prior to the hole-through,” reported Underground Construction, “the crews stopped within 9 feet of each other. The road header from Vargas then advanced until its spinning, titanium-studded knuckle broke through to the other side. Miners then made their way around their machines to shake hands and congratulate each other.”

On October 8, 2013, the contractor holed through the remaining 14,400 feet (4.4 kilometers) between Alameda West Portal and the Vargas Shaft: a monumental occasion for the City and the contractor’s very determined tunneling crews. The event was covered in a video report by TunnelTalk.

The Mott MacDonald construction management team, Contractor Designer, and SFPUC’s management worked together as a team to resolve construction issues collectively on a daily basis. “It was a real team effort as well as having multiple tools in the tool box to use to excavate and deal with the highly variable ground and groundwater that was encountered,” said Daniel McMaster.

Next, workers cleaned up the tunnel invert and installed panning to divert groundwater inflows into a collection of drainage pipes. Welded steel pipe with a diameter of 103 inches (2.6 meters) was installed in 50-foot (15-meter) lengths, and low-density cellular concrete was pumped in lifts to fill the annulus between the pipe and the tunnel walls. Contact grouting and mortar lining of the pipe were completed before the tunnel was connected to outside pipe work and finally commissioned.

Outcome

Construction was substantially completed in September 2015. The New Irvington Tunnel now carries drinking water to 2.6 million customers in San Francisco, San Mateo, Santa Clara, and Alameda Counties.

expand-image mail-envelope icon-icon-linkedin-mmdv-green icon-close arrow-left icon-section icon-section-white arrow-down icon-arrow-down-sml icon-arrow-left-lrg icon-arrow-left-sml icon-arrow-right-lrg icon-arrow-right-sml icon-arrow-up-sml icon-champions icon-section icon-section-white icon-download icon-education icon-email icon-grid-view icon-language icon-link-to icon-list-view icon-location icon-login-register ec-icon-login-register icon-ec-apply-arrow icon-ar-apply-arrow icon-mm-icon-search-ec icon-minus icon-more icon-phone icon-plus icon-recently-viewed icon-search icon hash key-facts-corner-sash quote-underline social-icon-facebook social-icon-googleplus social-icon-linkedin social-icon-twitter social-share-icon-facebook social-share-icon-facebook social-share-icon-googleplus social-share-icon-googleplus social-share-icon-instagram social-share-icon-instagram social-share-icon-linkedin social-share-icon-linkedin social-share-icon-twitter social-share-icon-twitter social-share-icon-youtube social-share-icon-youtube sina-weibo MM-Shape01-Quote-Views MM-Shape03-Quote-Locations MM-Shape05-Quote-Projects MM-Shape12-Quote-Sectors MM-Shape13-Quote-Expertise MM-Shape14-Quote-About-Us MM-Shape14-Quote-Careers checkmark icon-expand-view icon-apply-now menu linkedin-mmdv-green icon-ad-close mail-mmdv-green icon-ad-menu menu-close ec-menu-close sphere icon-cookies icon-legal icon-registered-companies target rotate-screen video-replay-flat video-replay audio-mute audio-play
×