Sixteen miles long, a light rail line called Link connects Seattle’s downtown area with SeaTac International Airport. One of the most challenging elements of this project was the deep mined Beacon Hill station and the one mile of twin “binocular” tunnels connecting it with Link.
The construction of the station required twin shafts and a complex configuration of vehicle, pedestrian, and ventilation tunnels ranging from 16 to 46 feet in diameter — all 160 feet underground.
Adding to the difficulty, the station and tunnels were constructed in ground that primarily consists of firm to hard clays but also includes zones of water-bearing sand and silt. According to the American Society of Civil Engineers, “the depth and dimension of the tunnels far exceeds anything done previously in soft ground in North America.”
As the lead joint venture partner, Mott MacDonald was responsible for overall project management and controls, and for the detailed design of all rail tunnels, portals, shafts, and mined station tunnels, including final linings and waterproofing.
The scope of work included scheduling, cost estimating, and contract drawings and specifications. Mott MacDonald provided design support during construction, including the engineering oversight of tunnels created using the sequential excavation method (SEM).
The Beacon Hill station was mined from two vertical shafts, excavated to a depth of 185 feet. The two shafts, one 46 feet in diameter and the other 26, act as entrances and exits and as ventilation structures.
SEM was used to construct the 380-foot-long platform tunnels, as well as concourse tunnels, cross-passage tunnels, ventilation adits, and concourse adits, which were 45 feet in diameter. Shotcrete was used for the initial linings.
The project included multistage excavation sequences, including twin sidewall drifts and single sidewall drifts. Stage-grouted barrel vault pipes and grouted pipe spiles formed the presupport for the SEM tunnels.
Twin 4,200-foot-long tunnels, one northbound and one southbound, were excavated using an earth pressure balanced tunnel boring machine. The tunnels were lined with one-pass precast segmental linings 18 feet 10 inches in diameter.
According to Sound Transit, “The Beacon Hill Tunnel is very important to the Link light rail system. By the year 2020, approximately 3,000 people per day will board the train at the Beacon Hill Station, making it one of the most heavily used stations south of downtown Seattle.”
Optical survey and geotechnical instruments were used to monitor buildings and utilities during construction and detect any settling of the ground. A 24-hour work schedule allowed the ground to be excavated and supported in a way that maximized safety and the stability of the soil. A noise wall was constructed to reduce noise from the site.
The twin tunnels were designed with three cross-passages to meet the egress requirements of the National Fire Protection Association’s NFPA 130 standard.
The Beacon Hill station was opened for revenue service in July 2009. It includes four high-speed elevators, emergency staircases, ventilation shafts, and artwork on the platform, concourse, head house, and plaza. Riders can descend to the train in 20 seconds.
Reporting on the American Council of Engineering Companies’ Platinum Award for 2010, which was awarded to this project, the Society for Mining, Metallurgy & Exploration (SME) cited our use of a “risk-based design approach” in which “the design team actually planned the complete excavation, including the initial and final support systems for the very large diameter shafts and very deep tunnels.”
SME continued, “This approach to deep complex tunneling in very poor soils, at a depth and a diameter close to twice that previously done, resulted in the largest soft ground SEM tunnel in North America.”
In addition, “Test shaft construction also led to the successful use of slurry wall construction for the time-critical vertical access shaft, and guided decisions on how to proceed with SEM tunnels, the use of steel fiber reinforced concrete for large diameter tunnels, and the use of fiberglass reinforcing in slurry walls. This process proved to be a significant advance in the design of SEM tunnels.”
The depth and dimension of the tunnels far exceeds anything done previously in soft ground in North America.American Society of Civil Engineers
We spoke with Eimon about what her typical day looks like, how active listening empowers collaboration, and her advice to professionals looking to grow their careers.
We caught up with Sander to explore his career journey, the role of trust in leadership, and how curiosity shapes his approach to urban mobility.
We caught up with transportation project manager Kundayi Mugabe to talk about his role within our business and the importance of being part of a team that supports peoples’ successes.
Wynton Habersham has joined Mott MacDonald as market leader for rail systems in the United States. In his role, he will lead the delivery of rail systems and train control professional services to clients in North America.
The new Line 6 Finch West LRT significantly improves connectivity for residents and commuters, easing congestion on major routes and providing thousands of daily riders with safe, reliable, and environmentally sustainable transportation.
The opening celebration kicked off with speeches from community leaders and a ribbon cutting ceremony in Federal Way, Washington, followed by a day of planned special events to commemorate the achievement.
Construction has begun on the Port Everglades Bulkhead Replacement Project in Fort Lauderdale, Florida – a vital seaport serving as a critical hub for cargo, petroleum, and cruise operations.
Toronto Pearson continues to advance its plans for Pearson LIFT - Long-term Investment in Facilities and Terminals, launching a competitive selection process for the T1/T3 Revitalization program and selecting Pearson Accelerator Construction Team (PACT) to lead the planning, design and construction of the Accelerator program.
As Calgary prepares for a future where its population could double by 2076, the city is investing in infrastructure that meets both today’s needs and tomorrow’s possibilities.
As Seattle prepares for significant population and job growth, the West Seattle and Ballard Link Extensions will add efficient light rail transit options to connect communities with reliable public transportation.
The Federal Way Link Extension light rail project will bring much-needed transit services to the Seattle region.