Locale : Global (English)
X
Create document Page
added
Remove
page
Add
page
Review document
/
Page Added
Collected
Pages
Create

Challenges of developing over-station projects Maurice Gidwani

In crowded and ever-growing cities, sites for development are increasingly sought after. But with swathes of land occupied by rail stations – and thousands of people travelling through them each day – it makes sense to develop over-station projects to deliver new facilities to local communities.

The role of stations themselves is changing, as they move away from being not just points of transit but are reimagined as hubs for commerce, recreation and retail. Stations such as Kings Cross, St Pancras and Liverpool Street are destinations in themselves, while station developments can also be the focal point for local or regional regeneration, as seen with HS1, Crossrail and the Northern Line Extension.

And over-station developments are likely to become more common. Soaring real-estate prices mean that local authorities and land owners seek to realise the maximum return on investments on their properties and better serve their communities. Transport for London, for example, aims to realise £3.4bn in non-fare revenue to reinvest in the transport network, much of which will come from land development.

Large-scale over-station projects can see new assets carefully superimposed on existing station infrastructure. A famous example of this is One Embankment Place, a commercial office block for PwC constructed above Charing Cross Station in central London. Less complicated projects refashion over-station buildings and infrastructure to meet new needs.

However, these developments come with challenges not found in other city-centre developments, which not only inform project design but also impact on project delivery.

Mitigate rail vibration

Mitigating vibration can be a key consideration to ensuring the viability of over-station developments, depending on the proposed use. Where possible, this should be done at the source of the vibrations – the wheel/track interfaces – although this is not always practical in adjacent or air rights projects where the station is itself not involved in the development, or due to cost considerations.

This process begins by examining the rail line for any wear from use or for distortions to the tracks as a result of ground movements over time. Track maintenance and realignment by the rail operator will correct these distortions and will go some way to reducing vibration.

The next stage of the process examines whether the tracks can be isolated to prevent the transmission of vibration to nearby assets. Rigid track sleepers with resilient mountings can be installed progressively during engineering hours and may be sufficient. Resilient clips or floating slab tracks can provide further mitigation, but would require a significant closure of the railway. All track-related mitigation would involve a compromise between the needs of the over-station development and the long term needs of the railway.

As for the over-station asset, elastomeric bearings between columns and the foundations may be necessary to mitigate vibration, although this will have implications for the design of the structure and allowance will need to be made for maintenance/replacement during the asset’s life.

Further, localised mitigation is possible by using design and construction based on ‘box-in-box’ techniques, often used in recording studios and cinemas, where the ceiling, walls and floor are resiliently mounted so that the space is isolated from the vibration in the building structure. However, this technique takes extra space and adds complexity to the project, while box-in-box rooms are difficult to adapt in the future.

Make use of existing piles

Not only is it possible to use existing piling for new built assets, it is highly desirable as reuse can bring cost savings and sustainability to the project. Removing old piles from the ground can be highly problematic and may disturb the ground so much that it becomes impractical to install new piling cost effectively.

Materials testing can confirm pile strength; non-destructive testing can confirm the integrity and lengths of existing piles; and back calculations can ascertain the loads that the piles previously supported. Combining this information with geotechnical analysis will demonstrate what the current piles can carry in the future, and additional piles can be inserted where existing infrastructure allows in order to support additional loads.

However, there are other considerations in the reuse of existing piles; in situ foundations combined with the insertion of new piles create congestion in the ground that impacts on the design of utility layouts.

Understand how new loads affect existing infrastructure

New loads transmitted via a building’s foundations into the ground will result in potential settlement and heave movements. Even small changes can be enough to affect track alignments, causing an increase in vibration, so it is important to understand when and where these movements will occur and their magnitude.

Where an over-station development uses both newly-inserted and existing foundations, there will be differential settlement. This needs to be carefully evaluated throughout the proposed construction sequence, which typically involves loads being removed during and following demolitions and then increased again following construction.

Separate construction work from rail operations

It is crucial that construction of over-station developments doesn’t impinge on functioning railways, and this imperative will affect construction techniques and programming.

Temporary or permanent walls may be erected and used to separate construction work from the rail station. If working over the rail line, a crash deck is usually needed which allows construction to take place without the risk of tools, components or materials falling onto the tracks.

While a temporary crash deck can be constructed, existing structures may be sufficient if investigation confirms this. Permanent works can be designed to provide the required levels of protection for new over-station developments.

For similar reasons, tower cranes may need to be limited in reach to eliminate the possibility of materials falling from jibs onto the tracks. It may be advantageous for components that need to be lifted to and around the site to be smaller, leading to a slightly longer lead-in time but usually a shorter overall project delivery time.

Where craning work must take place directly above the rail line, then it is often less disruptive to use a bigger crane and lift longer span components over tracks in one go, rather than use a small crane for several smaller component pieces. The need to minimise disruption will impact on programming, as work requiring the closure of rail lines will usually be done during short slot 'engineering hours' when the station is not in use, or at weekends or holidays when closing the line will have less impact. This favours the choice of construction methods where advances are made in short time windows.

This principle was put into practice at East Croydon rail station, where a new 98m vierendeel truss footbridge linking all platforms was built perpendicular to the railway and push-launched in one section across the station, minimising the disruption that would have resulted from craning smaller components into place for ground-up construction from each of the platforms.

If constructing part of the primary structure immediately above the platforms, then pile designs with a large bearing capacity will allow for a structure spanning greater lengths across the rail lines, avoiding the need to insert piles at more regular intervals and limiting how long the tracks need to remain closed. Large capacity can be achieved by capping clusters of multiple small diameter piles, avoiding use of large piling rigs. Taking this approach gets around height restrictions for plant used close to live rail lines, with potentially significant benefits for the project programme and cost.

Take advantage of DfMA

As well as bringing material and labour cost savings, the use of design for manufacture and assembly (DfMA) can cut onsite assembly time through the offsite production of prefabricated components.

The Northern Line Extension project – which will add two new train stations and 3.2km of twin bored tunnels to the London Underground network – will make ample use of prefabricated beams, columns, lattice slabs, twin walls and other elements, including the intent to adopt modular mechanical and electrical components. Use of DfMA on the project is expected to not only reduce construction time, but the simpler site logistics associated with DfMA will mean less disruption to residents across the area affected by the project.

Treat historical plans and records with caution

Finally, working with the UK’s rail stations often involves researching historical plans and records which provide invaluable information on the existing structure and infrastructure.

However, such documents may contain errors or inconsistencies and should not be relied upon in isolation. While historical documents can act as a very valuable guide, they should be accompanied by selective intrusive investigations and laser scanning to confirm the actual arrangement.

This article first appeared in Construction News on 10 July 2015.

expand-image mail-envelope icon-icon-linkedin-mmdv-green icon-close arrow-left icon-section icon-section-white arrow-down icon-arrow-down-sml icon-arrow-left-lrg icon-arrow-left-sml icon-arrow-right-lrg icon-arrow-right-sml icon-arrow-up-sml icon-champions icon-section icon-section-white icon-download icon-education icon-email icon-grid-view icon-language icon-link-to icon-list-view icon-location icon-login-register ec-icon-login-register icon-ec-apply-arrow icon-ar-apply-arrow icon-mm-icon-search-ec icon-minus icon-more icon-phone icon-plus icon-recently-viewed icon-search icon hash key-facts-corner-sash quote-underline social-icon-facebook social-icon-googleplus social-icon-linkedin social-icon-twitter social-share-icon-facebook social-share-icon-facebook social-share-icon-googleplus social-share-icon-googleplus social-share-icon-instagram social-share-icon-instagram social-share-icon-linkedin social-share-icon-linkedin social-share-icon-twitter social-share-icon-twitter social-share-icon-youtube social-share-icon-youtube sina-weibo MM-Shape01-Quote-Views MM-Shape03-Quote-Locations MM-Shape05-Quote-Projects MM-Shape12-Quote-Sectors MM-Shape13-Quote-Expertise MM-Shape14-Quote-About-Us MM-Shape14-Quote-Careers checkmark icon-expand-view icon-apply-now menu linkedin-mmdv-green icon-ad-close mail-mmdv-green icon-ad-menu menu-close ec-menu-close sphere icon-cookies icon-legal icon-registered-companies target rotate-screen video-replay-flat video-replay audio-mute audio-play
×
Mott MacDonald main logo

Would you like to hear more from us?

Sign up to receive notifications